General
These test procedures are to ensure the weathertightness of structures/shipboard outfitting,
the watertightness of tanks and watertight boundaries and structural adequacy of tanks.
Tightness of all tanks and tight boundaries of the ships at the new construction and, when
major conversions or repairs*
have been made, those relevant to the major
conversions/repairs should be confirmed by these test procedures prior to delivery of the
ship.
* Major repair means a repair affecting structural integrity.
Application
All gravity tanks** and other boundaries required to be watertight or weathertight
should be tested in accordance with this Guideline and proven tight and structurally
adequate as follows:
- - Gravity Tanks for their tightness and structural adequacy
- - Watertight Boundaries Other Than Tank Boundaries for their watertightness, and
- - Weathertight Boundaries for their weathertightness
** Gravity tank means a tank having a design working pressure not greater than 70 kPa at
the top of the tank.
The testing of cargo containment systems of liquefied gas carriers should be in
accordance with standards deemed appropriate by the Administration.
Testing of structures not listed in Table 1 or 2 should be specially considered.
Types of Tests and Definition of Test
The following two types of test are specified in this requirement:
Structural Test: A test to verify the structural adequacy of the construction of the tanks.
This may be a hydrostatic test or, where the situation warrants, a
hydropneumatic test.
Leak Test: A test to verify the tightness of the boundary. Unless a specific test is
indicated, this may be a hydrostatic/hydropneumatic test or air test. Leak
test with remark *3 in Table 1 includes hose test as an acceptable medium
of the test.
Definition of each type of test is as follows:
Hydrostatic Test:
(Leak and Structural)
A test by filling the space with a liquid to specified
head.
Hydropneumatic Test:
(Leak and Structural)
A test wherein space is partially filled with liquid and
air pressure applied on top of the liquid surface.
Hose Test:
(Leak)
A test to verify the tightness of the joint by a jet of
water.
Air Tests:
(Leak)
A test to verify the tightness by means of air pressure
differential and leak detection solution. It includes tank
air test and joint air test, such as compressed air test
and vacuum box test.
Compressed Air Fillet Weld Test:
(Leak)
An air test of fillet welded tee joint and leak indicating
solution applied on the fillet welds.
Vacuum Box Test:
(Leak)
A box over a joint with leak indicating solution applied
on the fillet or butt welds. Vacuum is created inside the
box to detect any leaks.
Ultrasonic Test:
(Leak)
A test to verify the tightness of a sealing by means of
ultrasonic.
Penetration Test:
(Leak)
A test to verify that no continuous leakages exist in the
boundaries of a compartment by means of low surface
tension liquids.
TEST PROCEDURE
General
Tests should be carried out in the presence of the Surveyor at a stage sufficiently close to
the completion of the work with all hatches, doors, windows, etc. installed and all
penetrations including pipe connections fitted, and before any ceiling and cement work is
applied over the joints.
Structural Test Procedures
Type and Time of Test
Where a structural test is specified in Table 1 or Table 2, a hydrostatic test in accordance
with 4.4.1 will be acceptable. Where practical limitations (strength of building berth, light
density of liquid, etc.) prevent the performance of a hydrostatic test, a hydropneumatic test
in accordance with 4.4.2 may be accepted as an equivalent method. Provided the results of a leak test are confirmed satisfactory, a hydrostatic test for
confirmation of structural adequacy may be carried out while the vessel is afloat.
Number of Structural Test
- Structural test should be carried out for at least one tank of same construction (i.e., same design and same workmanship) on each vessel provided all subsequent tanks are tested for leaks by an air test. However, where structural adequacy of a tank was verified by structural testing required in Table 1, the subsequent vessels in the series (i.e., sister ships built in the same shipyard) may be exempted from such testing for other tanks which have the structural similarity to the tested tank, provided that the water-tightness in all boundaries of exempted tanks are verified by leak tests and thorough inspection should be carried out. For sister ships built several years after the last ship of the series, such exemption may be reconsidered. In any case, structural testing should be carried out for at least one tank for each vessel in order to assure structural fabrication adequacy.
- For watertight boundaries of spaces other than tanks (excluding chain lockers), structural testing may be exempted, provided that the water-tightness in all boundaries of exempted spaces are verified by leak tests and thorough inspection should be carried out.
- These subsequent tanks may require structural test if found necessary after the structural testing of the first tank.
- Tanks for structural test should be selected so that all representative structural members are tested for the expected tension and compression.
Leak Test Procedures
For leak test specified in Table 1, tank air test, compressed air fillet weld test, vacuum box
test in accordance with 4.4.3 through 4.4.6, or their combination will be acceptable.
Hydrostatic or hydropneumatic test may also be accepted as leak test provided 4.5 and 4.6
are complied with.
Hose test will also be acceptable for the locations as specified in Table 1
with the foot note *3.
Joint air test may be carried out in the block stage provided all work of the block that may
affect the tightness of the joint is completed before the test. See also 4.5.1 for the
application of final coating and 4.6 for safe access to joint and their summary in Table 3.
DETAILS OF TEST
Hydrostatic Test
Unless other liquid is approved, hydrostatic test is to consist of filling the space by fresh
water or sea water, whichever is appropriate for testing of the space, to the level specified
in Table 1 or Table 2.
In case a tank for cargoes with higher density is to be tested with fresh water or sea water,
the testing pressure height should be specially considered.
Hydropneumatic Test
Hydropneumatic test where approved should be such that the test condition in conjunction
with the approved liquid level and air pressure will simulate the actual loading as far as
practicable. The requirements and recommendations for tank air tests in 4.4.4 will also
apply to hydropneumatic test.
Hose Test
Hose test should be carried out with the pressure in the hose nozzle maintained at least at
2·105
Pa during the test. The nozzle should have a minimum inside diameter of 12 mm and
be at a distance to the joint not exceeding 1.5meters.
Where hose test is not practical because of possible damage to machinery, electrical
equipment insulation or outfitting items, it may be replaced by a careful visual examination
of welded connections, supported where necessary by means such as a dye penetrant test or
ultrasonic leak test or an equivalent.
Tank Air Test
All boundary welds, erection joints and penetrations including pipe connections should be
examined in accordance with the approved procedure and under a pressure differential
above atmosphere pressure not less than 0.15·105
Pa with a leak indication solution applied.
It is recommended that the air pressure in the tank be raised to and maintained at about
0.20·105
Pa for approximately one hour, with a minimum number of personnel around the
tank, before lowered to the test pressure of 0.15·105
Pa.
A U-tube with a height sufficient to hold a head of water corresponding to the required test
pressure should be arranged. The cross sectional area of the U-tube should be not less than
that of the pipe supplying air to the tank. In addition to U-tube, a master gauge or other
approved means to verify the pressure should be approved.
Compressed Air Fillet Weld Test
In this air test, compressed air is injected from one end of fillet welded joint and the
pressure verified at the other end of joint by a pressure gauge on the opposite side. Pressure
gauges should be arranged so that an air pressure of at least 0.15·105
Pa can be verified at
each end of all passages within the portion being tested.
Note: Where the leak test is required in way of the fabrication applying the partial
penetration weld, compressed air test is also applied in the same manner for fillet
weld where the root face is sufficiently large, i.e., 6 – 8 mm.
Vacuum Box Test
A box (vacuum tester) with air connections, gauges and inspection window is placed over
the joint with leak indicator applied. The air within the box is removed by an ejector to
create a vacuum of 0.20·105
– 0.26·105
Pa inside the box.
Ultrasonic Test
An arrangement of an ultrasonic echoes sender inside of a compartment and a receiver
outside. A location where the sound is detectable by the receiver displays a leakage in the
sealing of the compartment.
Penetration Test
A test of butt welds by using of a low surface tension liquid at one side of a compartment
boundary. If no liquid were detected on the opposite sides of the boundaries after expiration
of a definite time this means the verification of tightness of the compartments boundaries.
Other Test
Other methods of testing may be considered by each society upon submission of full
particulars prior to commencement of the testing.
APPLICATIONS OF COATING
Final Coating
For butt joints by automatic process, final coating may be applied anytime before
completion of leak test of the space bounded by the joint.
For all other joints, final coating should be applied after the completion of leak test of the
joint.
The Surveyor reserves a right to require leak test prior to the application of final coating
over automatic erection butt welds.
Temporary Coating
Any temporary coating which may conceal defects or leaks should be applied at a time as
specified for final coating. This requirement does not apply to shop primer.
Safe Access to Joints
For leak tests, a safe access to all joints under examination should be provided. See also
Table 3.
Knowledges From : IACS Guideline for Procedures of Testing Tanks and Tight Boundaries
Tidak ada komentar:
Posting Komentar